ADU Under 750 Sq Ft in Burbank & Glendale: 2026 Fee Rules
In California in 2026, a city or special district may not charge development impact fees on an ADU with 750 square feet or less of interior livable space, or on a junior ADU of 500 square feet or less (Government Code section 66311.5). Above 750 square feet, impact fees can be charged, but only in proportion to the size of the main house. Separately, an ADU with less than 500 square feet of interior livable space does not count as added assessable space for school fees. In Glendale Unified the residential school fee is $5.38 per square foot, so the 500 line can be worth several thousand dollars. Connection fees, capacity charges, permit and plan check fees are not covered by the 750 rule.
Two numbers do a lot of quiet work in ADU budgets this year: under 500 and 750 square feet. Cross the first and a school fee appears. Cross the second and city impact fees can apply. Neither number changes what it costs to frame a wall or set a cabinet, but both change the check you write at the permit counter.
This guide is for homeowners in Burbank and Glendale who are still deciding how big the unit should be. It covers what the state rules say, how they play out in each city, and what is still charged no matter how small the unit is.
The two thresholds, in plain terms
California reorganized its ADU law in 2024 and amended it again for 2026. The fee rules now sit in Government Code section 66311.5. The state housing department (HCD) summarized the 2025 changes in a December 2025 letter to the City of Burbank:
- 750 square feet. A local agency may not charge impact fees on an ADU that has 750 square feet of interior livable space or less, or on a junior ADU (JADU) of 500 square feet or less. For an ADU larger than 750 square feet, any impact fee must be charged proportionately in relation to the square footage of the main house.
- Under 500 square feet. An ADU or JADU with less than 500 square feet of interior livable space does not increase assessable space. In practice, that is the test school districts use to decide whether a developer fee applies.
Note the wording. The impact fee rule says "750 or less." The school fee rule says "less than 500." A 750-square-foot unit avoids impact fees; a 500-square-foot unit does not avoid the school fee. A 499-square-foot unit does.
What changed in how the square feet are counted
Until 2026, a lot of ADU math was done from the outside of the walls. HCD's letter notes that the size limits are now based on the square footage of interior living space. That sounds like a technicality. On a small unit it is not: the thickness of exterior walls on a detached ADU can add up to several dozen square feet that no longer count against the limit.
Our practice is simple. We put a separate area calculation sheet in the drawing set that shows the interior livable area room by room, and we confirm with the plan checker how they want it shown before submittal. It is much easier to fix a number on paper than to argue about it after plan check comments come back.
Glendale: what the numbers look like
Glendale permits a lot of ADUs. In 2025 the city issued building permits for 695 ADUs, according to the Annual Progress Report data the state publishes, about 44 percent of all housing units Glendale permitted that year.
For school fees, Glendale Unified publishes a residential developer fee of $5.38 per square foot. That matches the 2026 state maximum set by the State Allocation Board in January 2026. So the arithmetic for a detached ADU in Glendale Unified territory looks like this:
| Interior livable area | School fee at $5.38/sq ft | City impact fees |
|---|---|---|
| 495 sq ft | $0 (under 500) | None (750 or less) |
| 700 sq ft | $3,766 | None (750 or less) |
| 760 sq ft | $4,088.80 | May apply, proportional to the main house |
The school fee column is our arithmetic from the published rate, not a quote; your district confirms the final number when it issues the fee certificate. For how Glendale's permit process compares with its neighbors, see permits in Glendale vs Burbank vs Los Angeles and our Glendale page.
Burbank: why the size decision matters even more
In Burbank, ADUs are most of the new housing. Of the 284 housing units the city permitted in 2025, 241 were ADUs, roughly 85 percent, based on the same state Annual Progress Report data.
Two things are worth knowing before you design:
- School fees. These are collected for Burbank Unified. The state maximum for 2026 is $5.38 per square foot, but we did not find a current rate published by the district, so confirm it directly before you lock the size. The state rule on units under 500 square feet applies here too.
- The local ordinance. In its December 2025 technical assistance letter, HCD noted that the most recent Burbank ADU ordinance on file with the state dated from 2020 and listed the state law changes since then that may warrant an update. If a city handout and current state law disagree on size or fees, ask which one the city is applying, in writing. We cover the local steps on our Burbank page.
What the 750 rule does not cover
The impact fee rule is generous, but it is narrow. A unit of 750 square feet or less still pays:
- Building permit and plan check fees, based on the city's fee schedule and the project valuation.
- Utility connection fees and capacity charges. State law treats these separately from impact fees. Whether an ADU triggers a new connection depends on how it is served; a conversion inside the existing house is treated differently from a new detached unit.
- School fees, if the unit is 500 square feet or larger.
We walked through the full permit budget in what an ADU permit costs in Los Angeles.
Designing around the lines without shortchanging the unit
Hitting a threshold is not a goal by itself. A one-bedroom at 740 square feet that works well will rent and live better than a cramped 499-square-foot unit squeezed to save a fee. The point is to make the size decision on purpose, early, with the numbers in front of you.
A few things we look at in the first meeting:
- Conversion or new build. A garage conversion often lands under 500 square feet on its own; see garage conversion ADU costs.
- ADU or JADU. A JADU is limited to 500 square feet inside the house and has its own rules; see ADU vs JADU.
- How many units fit. The size of one unit affects what else the lot can hold; see how many ADUs you can build in 2026.
- Timelines. Under the same 2025 changes, the city has 15 business days to tell you in writing whether your application is complete and, if not, what is missing.
If you are weighing 495 against 700 against 800 square feet, we can lay out the fee side of each option before the drawings are final. That is how every ADU and addition project starts with us.
Sources
- California Department of Housing and Community Development, letter of technical assistance to the City of Burbank on its ADU ordinance, December 5, 2025 (summarizes Gov. Code §§ 66311.5, 66317, 66321).
- State Allocation Board, index adjustment on developer fees, approved January 28, 2026.
- Glendale Unified School District, Developer Fees.
- California Department of Housing and Community Development, Housing Element Annual Progress Report data, data.ca.gov (building permits by unit type, 2025).
DN Builders Group Inc is a licensed, bonded general contractor based in Burbank (CA Lic. #1139710), working across Greater Los Angeles on ADUs, additions, kitchens, bathrooms and whole-home renovations. This post is general information about California rules, not legal advice; fees change, so confirm current amounts with your city and school district before you finalize a design.
Questions
Does an ADU under 750 square feet pay any fees at all?
Yes. Government Code section 66311.5 bars development impact fees on an ADU of 750 square feet or less of interior livable space, but it does not cover building permit and plan check fees, and impact fees do not include utility connection fees or capacity charges. School fees follow a separate threshold of under 500 square feet.
How much is the school fee on an ADU in Glendale?
Glendale Unified publishes a residential developer fee of $5.38 per square foot, which matches the 2026 state maximum set by the State Allocation Board. An ADU with less than 500 square feet of interior livable space does not count as added assessable space, so it is not charged. For a 700-square-foot ADU the arithmetic is 700 times $5.38, or $3,766, before any other fees.
What about school fees in Burbank?
School fees in Burbank are collected for Burbank Unified, and the state maximum for 2026 is $5.38 per square foot of residential construction. We did not find a current rate published by the district, so confirm it with Burbank Unified before you finalize the size of the unit. The state rule that an ADU under 500 square feet does not add assessable space applies in Burbank as everywhere in California.
Is the 750 square feet measured from the outside walls?