Change orders in California: what must be in writing
In California, a change order on a home improvement contract has to be in writing and signed by both you and the contractor before the extra or changed work begins. Under Business and Professions Code section 7159.6, it must state three things: the scope of the change, how much it adds to or subtracts from the contract price, and how it affects the payment schedule or the completion date. A verbal "go ahead" on site is not enough, and a contractor cannot hold you to a price you never saw in writing.
Why change orders matter more than the original bid
Almost every remodel changes after it starts. You see the cabinets in place and want one more drawer stack. Demolition opens a wall and the framing is not what anyone expected. A tile is discontinued. None of this is unusual, and none of it is a problem by itself.
The problem is how the change gets recorded. A conversation in the driveway or a text that says "sounds good" is how most remodel disputes begin: two people remember the same moment differently, and the final invoice is where they find out.
California does not leave this to good manners. The home improvement contract law spells out how changes must be documented, and it puts the burden on paper.
What the law requires
Two sections of the Business and Professions Code cover this.
Section 7159 sets the rules for home improvement contracts. It requires a change-order form for changes or extra work to be part of the contract, and it says any change to the contract must be in writing and signed by the parties before the work covered by the change begins. The contract must also include a notice telling you how extra work and change orders work.
Section 7159.6 is the short, practical one. A change order is not enforceable against the homeowner unless it states:
- the scope of work covered by the change,
- the amount added to or subtracted from the contract price, and
- the effect on progress payments or on the completion date.
The same section says a homeowner may not require a contractor to do extra or changed work without written authorization. The rule protects both sides: you are not on the hook for surprise extras, and the contractor is not expected to work on a handshake.
The Contractors State License Board puts it in plain terms for homeowners: if you add or subtract work, substitute materials or change the completion date, note it in writing on a change order with any price change, and once signed, it becomes part of the written contract.
The part people misread
Some homeowners take the rule to mean "if it is not written, I never have to pay." That is not quite what the statute says. Section 7159.6 also states that a contractor's failure to follow it does not bar recovery for work actually performed under legal remedies designed to prevent unjust enrichment.
So the writing requirement is not a trap for either party. An unwritten extra does not disappear; it turns into an argument about value that costs more than the change did.
How the schedule and payments move
The third required item, the effect on payments or completion date, is the one most often skipped, and it matters.
California also limits how far payments can run ahead of the work. Apart from the down payment, a contractor may not request or accept payment that exceeds the value of work performed or materials delivered (we cover the deposit rule in our post on how much deposit a contractor can ask for in California). The LA County Department of Consumer and Business Affairs gives the same advice in its tips for hiring a contractor: do not let payments get ahead of the work actually completed.
A change order that adds work should say where the added amount lands in the payment schedule, tied to a milestone, not "due now." If the change adds two weeks because a special-order window has a longer lead time, the new completion date should be on the same page.
Changes that touch the permit
Not every change is a paperwork-only change. Replacing one tile with another does not affect your permit. Moving a wall, adding a window, rerouting a drain line or adding circuits can change what the approved plans show. In those cases the building department may need to see the revision before the inspector signs off on that stage.
That is one reason older houses generate more change orders than newer ones. In a 1950s Valley ranch, what is inside the walls is often the real scope, as we explain in what's behind the walls of a 1950s San Fernando Valley house. A good change order on a job like that says what was found, what has to change and whether the drawings change with it.
A simple checklist before you sign a change order
- It has a number and a date, and it refers to your original contract.
- The scope is specific. "Upgrade shower" is not a scope. "Replace standard valve with thermostatic valve, add one wall niche 12 by 24 inches" is.
- The price change is a dollar figure, added or subtracted, not "time and materials, TBD."
- The payment schedule is updated, so you can see when the new amount is due and which milestone triggers it.
- The completion date is restated, even if it does not change.
- Both of you sign before the work starts. A change order signed after the work is done is a record, not an agreement.
- The contractor's license is active. It takes a minute to confirm; see how to check a contractor's license in Los Angeles.
How we handle changes
On our kitchen and bathroom projects, a change starts with a short written description and a price before anything is ordered or built. You see the scope, the dollar amount, where it falls in the payment schedule and what it does to the finish date, and you sign it or you do not. If the change affects the permitted plans, we say so on the same page and handle the revision with the building department.
It slows the decision down by a day. It saves weeks of arguing at the end.
Sources
- California Business and Professions Code section 7159 and section 7159.6 (California Legislative Information).
- Contractors State License Board, What should I look for in a contract?
- Los Angeles County Department of Consumer and Business Affairs, Hiring a Contractor.
DN Builders Group Inc is a licensed, bonded general contractor based in Burbank (CA Lic. #1139710), working across Greater Los Angeles on kitchens, bathrooms, additions, ADUs and whole-home renovations. This post is general information about California law, not legal advice. For advice on your situation, consult an attorney or contact the Contractors State License Board.
Questions
Is a verbal change order legal in California?
For a home improvement contract, changes must be in writing and signed by the parties before the covered work starts (Business and Professions Code sections 7159 and 7159.6). A verbal agreement on site does not meet that standard.
What should a change order include?
The scope of the added, removed or substituted work; the dollar amount it adds to or subtracts from the contract price; and its effect on the progress payment schedule or the completion date. It should be dated, numbered and signed by both parties before the work begins.
Can a contractor charge for extra work I never approved in writing?
An unwritten change order is not enforceable against you as a change order, but the law still lets a contractor seek the fair value of work actually performed under unjust-enrichment remedies. For help with a dispute, contact the Contractors State License Board or the LA County Department of Consumer and Business Affairs.
Do change orders affect the permit?
Sometimes. A different tile or faucet does not. Moving a wall, adding a window, relocating plumbing or adding circuits can change the approved plans, and the building department may need to review the revision before the inspector signs off.